When developing probabilistic estimates of project duration, it is necessary to know which of the following:
A) the mean and variance of every activity
B) the mean and variance of activities on the critical path
C) the standard deviation of activities on the critical path
D) each activity's probability of completion
E) the distribution of activity times

Respuesta :

Otras preguntas

Which components exist in the contextual tab for tables called Design? Check all that apply. Table Styles Export Table Data Properties Tools Banded Rows Externa
(9x+6)° and (6x+9)° What is the answer
Tu (aimer) regarder la télé avec tes copines. Correct form of the verb?
* 4. Find the measure of each angle Please help need answers ASAP
A car dealer buys a car for $500, and then sells it for $640. Whatis the percentage profit?is sold for $100.​
3 examples of inherited variation in dragon fruit​
Find the equation the line with the given information below: X-intercept = (-4, 0) y-intercept = (0, -8)
Read the excerpt from Queen Elizabeth's Address to the Troops at Tilbury. Let tyrants fear, I have always so behaved myself, that, under God, I have placed my c
Discuss respect in terms of conducting research
all water on earth is recycled through