Using the PERT estimate, calculate the estimated duration of an activity given:
Optimistic Estimate = 21 days
Pessimistic Estimate = 110 days
Most Likely Estimate = 55 days
a) 62.5 days
b) 74 days
c) 65 days
d) 68.5 days

Respuesta :

Otras preguntas

do humanity’s moral standards change with time, or are there certain things that would shock people in any area?
what will be number of zeros in the square of the number 100? pls answer fasttttttttttt
Helppppp hurryyyy What made the 99th Pursuit Squadron, also known as the Tuskegee Airmen, a unique combat unit in World War II? A It was the first all-black com
In ancient Egyptian society, which duties did the upper class perform? Help I’m timed
what is the square of 3844​
Write a letter to the headmaster why the school should instill on moral lesson into the students
A ballroom is 60 ft long and 30 ft wide. Which of the following formulas is the correct formula to determine the perimeter of the ballroom
two practical strategies that could be implemented by the community to ensure that the anti substance abuse campaigns are effective
how many energy levels do aluminum, argon and sodium have?plz help
Explain demand paging with a proper example