If you want to give a vendor an incentive to complete work early, which type of contract would you use?


Respuesta :

leiraallen
leiraallen leiraallen
  • 16-05-2020

fixed price contract: The vendor will be paid a fixed payment regardless his time spending. Thus the vendor will try to complete work as soon as possible, then he can receive his payment/ incentive for completed work

Answer Link

Otras preguntas

The work of a planning aide is essential to hospital managers social workers housing developers emergency managers What is the answer
needs help with this!!!
Find the length of each arc. Round your answer to the nearest tenth. Show your steps, equations, and work.
5. What is the difference in the solution to the problem (a) and problem (b) below: a) Solve 2 – 3 < 5 and 20 +4 < 14 b) Solve 1 – 3 < 5 or 2x + 4 <
A toy is marked up 25% from the original price, x. Write two expressions to find the price of the item after the discount.
What is true about asteroids
Where does the urea in the urine come from?
Please help me it is urgent
4.678 written to one decimal point would be​
What is most plastic made of? A) synthetic materials B) carbon containing compounds C) inorganic compounds D) organic compoundsE) petroleum or coal materials​