Three men working together can finish a house repair job in 10 days. How manydays will 5 men working at the same rate finish the same job? *

Respuesta :

berno berno
  • 12-04-2021

Answer:

17 days

Step-by-step explanation:

Number of days in which 3 men can finish a house repair job = 10 days

Number of days in which 1 man can finish a house repair job = [tex]\frac{10}{3}[/tex] days

Therefore,

Number of days in which 5 men can finish a house repair job = Number of days in which 1 man can finish a house repair job × 5

[tex]=\frac{10}{3}(5)=\frac{50}{3}=16.6[/tex] ≈ 17 days

Answer Link

Otras preguntas

d) i/shopping/but/sister/doesn't/do/itplease rearrange it​
can someone please help me​
Hi Guys Please answer this question. I will choose Brainliest. Worth 10 points and it is a Maths question. Cheers, Jake
Read the lines from "Playing Robinson Crusoe." ***** will rub my knees with her head, Pretending she loves me hard; But the very minute I go to my bed ***** run
Need help with Spanish homework plz help!
What is 40 percent of 50? 1. 20 2. 30 3. 40 4. 10
Find the equation of the line below
Which is a complete sentence? O 1. Single file from the gym to the field. 2. The whole class stood in line. 3. Everybody quiet listening to the music. 04. Flags
hurry this is a test please answer correctly ​
Which of the following best explains why Earth is tectonically active? A. Areas of Earth's solid surface layer are thicker and so heavier than other areas. B. A