If 4 electricians can wire some new houses in 20 days, how many electricians would be required to do the job in 10 days?
a. 30
b. 8
c. 45
d. 2

Respuesta :

frozenpods
frozenpods frozenpods
  • 13-02-2022

Answer:

2

Step-by-step explanation:

20/2 = 10

4/2 = 2

Answer Link

Otras preguntas

you are paid $82.50 for 7 1/2 hours of work, whats is your rate of pay?
The ability to regulate the amount of charge flowing in a circuit is A. alternating current. B. direct current. C. resistance. D. voltage.
One of the main ways that humans can cause a desert to appear where one did not exist before is by blank
All houses are built according to safety standards, so it is not important to consider injury prevention while at home. T F
Which of the following pairs of words does NOT contain an adjective? a. spicy seasoning b. savory marinade c. astonishing cooking d. bake carefully
Which of these is NOT something you need to check when you are revising a personal narrative? A. word choice B. capitalization C. structure D. margins
The available source of charge that pushes a charge through a circuit is A. alternating current. B. direct current. C. voltage. D. resistance.
What are the specific difference between bulimia nervosa and binge-eating ? What are the specific difference between bulimia nervosa and binge-eating disorder?
what is the equation of the line that is parallel to the line 5x+2y=12 and passes through the point (-2,4)?
What determines how quickly a rock is weathered