When you state exactly when you must complete your goal, this is which part of the SMART goal?
M for Measurable
A for Attainable
R for Realistic
T for Timely

Respuesta :

sara153 sara153
  • 16-02-2017
T for timely. Hope this helps!
Answer Link
paigeryan001 paigeryan001
  • 25-03-2021

Answer:

T for timeley

Explanation:

Answer Link

Otras preguntas

What is the name given to the process shown in the diagram
NEED HELP ASAP thanks + BRAINLIST only for correct answer
pls help it's due in an hour​
que ocurre con las lenguas en México???aiudaaaa​
Given f(x) = x⁴- 3x³ + 9x²- 17x + 42 and g(x) = -x² - x - 6, where g(x) cant equal 0, find (f/g)(x)​
An artillery shell is fired with an initial speed of 300m/s at 55 deegry about the horizontal,it explodes on a mountain side 42s after firing,what are the x and
What is the distance between point (-2,2) (4,4)
The amount of money Elise earned in tips per day for 6 days is listed below. $75, $97, $360, $84, $119, $100. Calculate the mean and median amount earned
Debra walked her dog to the south. They walked 50 meters in 150 seconds. What was their velocity? A. 12 m/s south B. 3 m/s south O c. 100 m/s south D. 0.3 m/s s
A). es importante yconocer los sintomas y caracteristicasde la adiccion con el proposito de prevenirla​